Management contract: outline work plan
An outline work plan for a project following a management contract procurement route is presented below. Project plans for other procurement routes are available by clicking here.
Clicking on any of the stages will open up the detailed tasks necessary to complete that stage. Together the tasks represent a single, consolidated project plan from the first moment it becomes apparent a project might be required right through to post occupation evaluation.
See also: Management contracting - pros and cons.
[edit] Management contract
Stage 1: Business justification.
Stage 2: Feasibility studies.
Stage 3: Project brief.
Stage 4: Concept design.
Stage 5: Appointing the management contractor.
Stage 6: Detailed design.
Stage 7: Production information.
Stage 8: Tender works contracts.
Stage 9: Mobilisation.
Stage 10: Construction.
Stage 11: Occupation and defects liability period.
Stage 12: Post occupation evaluation.
Moveable stages:
Featured articles and news
What to do with troublesome statues?
A tricky political issue.
Designing Buildings content from and for its users
Discover more on how simple and quick it is to publish an article.
Recent users articles; Timber and retrofit
Which products, for what reasons.
Recent users articles; Digitally Built Britain
ISO 19650, BIM and data management.
Recent users articles; Interim valuations and payments
Applications, notices ad points to remember.
Recent users articles; What is H-Scaffolding?
Elements, features and areas of use.
Recent users articles; what are NZEBs ?
How do they contribute to Sustainable Development.
The most viewed articles in 2022 on Designing Buildings
Written in the past 6 months, one year and beyond.
Second stairs for new tower blocks
Government launches a 12-week consultation
Happy Festive Holidays to all our users from here at DB
On the first day of Christmas DB for the Industry...
The psychological power of the built environment.
IHBC signpost update from Lords Committee on climate
Government must support behaviour change to meet targets.
Reflecting on 2022 into 2023 with the APM WiPM SIG
Women in Project Management conference 2022.
Types, colours and processing of hydrogen on DB
Grey, green, purple, blue, yellow, turquoise, brown and black.
The Kyoto Protocol a brief reminder on DB
Adopted in 1997, ratified in 2005..
Europe moves to phase out electrical SF6 gas
Sulphur hexafluoride the world’s most potent GHG.
Biomass boiler market on the rise in Europe
Proving to be a driver for decarbonisation targets.
Comments
What is a client coordinated approach to major project and what are key elements to consider? Any contribution to this,please.
Have a look at this and related articles: https://www.designingbuildings.co.uk/wiki/Major_project_definition